Major improvements to Lymington flood defences completed

Imported from official source

Disasters Classified by Officially

The Environment Agency has completed a two-year project to replace tidal outfall flaps and improve flood defences at Toll Road in Lymington, ahead of the winter flood season. 

The project replaced the original steel tidal flaps, installed around 18 years ago as part of the Lymington Flood Alleviation Scheme, which had reached the end of their design life and become heavily corroded in places.

Following detailed surveys, including underwater inspections by specialist divers, new flaps made from high-density polyethylene and marine-grade stainless steel were designed, manufactured and installed in September 2026 during low tide, using divers and a crane.

The new material offers a more durable solution for the tidal environment, with reduced maintenance needs and improved reliability.

The original steel tidal flaps were installed around 18 years ago

The flaps form part of the wider Lymington Flood Alleviation Scheme, which also includes piling along the marshes to protect nearby homes, and a flood gate at Toll Road that can be closed to prevent flood water reaching the town.

As part of this project, the Environment Agency also repainted the flood gate, replaced worn seals, improved pedestrian access when the gate is closed, and installed a new, quieter road surface.

Works were planned to minimise disruption and carried out outside school holidays. 

The team found that leaking floats had affected the regulating valve

During the project, the team found that leaking floats had affected the regulating valve, which manages water levels in the marshes and is particularly important for flood risk management in winter.

Replacement floats have been ordered and will be fitted when conditions allow. In the meantime, the valve has been temporarily closed as a precaution, meaning residents may notice lower water levels in the marshes.

Normal operation will resume once the floats are replaced.

New flaps made from high-density polyethylene and marine-grade stainless steel were designed

This is an extract. The publication continues at the source.

Contains public sector information licensed under the Open Government Licence v3.0. Licence

Read the original at the source: https://www.gov.uk/government/news/major-improvements-to-lymington-flood-defences-completed

Officially imported this from Environment Agency’s own source and shows an extract. If you work there, claiming the profile and verifying the domain lets you choose to show the full text here.

Provenance

Organization
Environment Agency — imported from official source
Official source
https://www.gov.uk/government/organisations/environment-agency.atom ATOM
Imported
October 07, 2026 10:00
Versions
1 recorded
Identity
https://www.gov.uk/government/news/major-improvements-to-lymington-flood-defences-compl...

Officially records where a publication came from, not whether it is true. Imported records are reproduced from an organization's own official source.